PROGRESS REPORT ON WORKS AT OUR SCHOOLS

  • On Thursday 128.2 cubic metres of concrete made in Sunbury was laid for the ground floor of O.L.M.C. School. They worked a 14-hour day.
  • The next storey will be laid next month.
  • The new lift has been purchased.
  • At St Anne’s, the plasterers are about to begin. Both projects are moving quickly.